Mill 240

Owner:

SM Development

Tenant:

Site Address:

Client:

Architect:

General Contractor:

PC Construction

Institution:

Location:

Lawrence, MA

Project Size:

$4,000,000.00

Project Cost:

SQFT:

380,000

System Size:

Number of Modules:

Field Manager:

Electrical Foreman:

Low Voltage Foreman:

DEI Systems completed this 2 building project with PC Construction in March of 2019. The project consists of a 7 story, 344,000SF mill remodel featuring (198) 1 and 2 bedroom apartments, 60,000SF self-storage facility and a 42,000SF ground level parking garage.  Community features include a roof deck, cyber café, fitness/yoga studio, community room and riverfront park.  An additional 29,000SF single story building houses (19) luxury studio units with high ceilings and polished concrete floors.

DEI Systems was responsible for the following scope of work:

  • Electrical Construction
  • Extensive Lighting Package
  • Distribution Equipment
  • Fire Alarm System (High Rise Voice)
  • Intercom System
  • Video Surveillance
  • 350Kw Emergency Generator
  • Datacom
  • Bi-Directional Antenna System (State and Local Frequencies)